Proposed Construction of Landfill Gas Collection
Phase 3 in Bukit Tagar Sanitary Landfill
Pipe Laying & Welding
Pipe Laying & Welding
Laying Pipe at Slope Phase 2B
Project Info
- Supply and install 315mm diameter double flanged butterfly valve with streering wheel at booster station (GBS) for isolating
To supply and install add HDPE 315mm x 250mm dia. T junctions
- Well No. 3 – 15
2. Well No. 3 – 18
Laying Pipe at Slope Phase 2B
- Connection of proposed 315mm dia. HDPE pipe to existing Gas Booster Station inclusive of cutting, welding, short piece and any other necessary works.